Status Report - HERO: Week of 09.27

Posted:September 27, 2015

The Fukumatsu Residence is almost finished for this phase of development. Doors and ceilings have been installed in all the rooms. As I stated before, detailing the rooms will happen when I know what specifics they need. In counter to the potential of the individual rooms, the hallway is finished in neutral tones, dark gray walls with white trim.


Example Room
Hallway

Outside, the basics of the patio and garden have been designed. The stone patio is attached to the ballroom and overlooks the beach down below. The garden centers around a long reflecting pool. Flora will be planted around the edges to enclose the space and make it feel more intimate.


Patio
Garden

Once I finish up with the last of the detailing here, I'll move back into town to reacquaint myself with it as I've been in the Fukumatsu Residence for a while. I will most likely then work on the Kuroto and Akimori Residences. Those are quite important so I'll be spending lots of time working on them.


All images are unrendered, raw SketchUp models.

Nick